PLEASE NOTE. This is a very early launch of a platform designed to update stakeholders and observers of Its Time solar schools’ projects. Current, historical and up-coming projects will be gradually added. As will the various information panels below. It is a considerable development project and we appreciate your patience as it evolves over the coming weeks. Almost certainly there will be a bug or two along the way - should you notice any issues or have ideas to improve the platform, your message is appreciated message via: iitime.org/contact-us

Banaban School Rabi  (1233 Cakaudrove)

About

Docs & Links

Specifications

Works & Maintenance

CO2 & $s

Contacts

Charge data

Term Reports

Procedures

Google map

About

The Banaban Primary School is on Rabi Island. From Suva that means an overnight ferry trip, two hours in a truck and a sea crossing the get to the school.

Prior to solar the school had been running a generator for several hours each day and in the evenings during exams periods for night study. As well as fuel costs they have had issues with the generators needing repairs or replacement - they are now on to their third generator in in five years. Now they have solar, using the fuel savings the school leadership is keenly focused on building the schools’ capacity to deliver a modern education with electronic resources - recently purchasing laptops and projectors to facilitate modern education at the school. That and the now reliable 24 hour power is making serious difference at the school.

The school has committed to spend 15 minutes each week picking up plastics – less waste and great learning for the kids. The school has also taken on other clean ups and village beautification projects including converting old bins and tyres into planter pots etc. The school has become a true community leader for sustainability on the island. Check out their website: https://www.banabanps.com/

School Role & Facilities
Students:
Teachers:
Classrooms:
Kindergarten:
Offices:
Library/computer area:
Teachers homes in the school grounds:
Boarders (live-in students):
Hostels (Boarding houses):
Dining rooms:
Date entered:
Project Funding

Lead funding was seven shareholders from CWP Global lead by Michael Vawser (thanks Ed, Alex, Kam, Mark, Mike, Dimitar and Helen). Thanks to all our supporters The students, teachers, school management committee and the whole community send a big Vinaka Vakalevu – thank you. The project was installed June 2022.

Our school commits to have a group of students spend at least 15 minutes, most weeks, picking up plastics. So, we keep our small patch on the earth as free of plastic as possible - its a small action we do to protect marine and other wildlife. We hope all schools in the world join us in doing the same.

Carbon Dioxide and Financial Savings
Document
As well as fuel costs they have had issues with the generators needing repairs or replacement - they are now on to their third generator in in five years. So in this schools' case the estimate for generator maintenance is significantly underestimated.

Banaban School Rabi

Annual school fuel saving (litres) (1)

1,900

Annual fuel saving 1 teachers' homes getting solar (litres) (2)

50

Annual cartage saving (litres) (3)

285

Total annual fuel saving (litres) (4)

2,330

Fuel saving over 30 years (litres)

69,900

Annual CO2 saving (kgs)

5,941

CO2 saving over 30 years (kgs)

178,245

Annual AUD saving (8)

$ 6,060

Annual USD saving

$ 4,120

Annual FJD saving

$ 9,090

30 yrs AUD saving

$ 181,800

30 yrs USD saving

$ 119,730

30 yrs FJD saving

$ 264,150

Total of All It's Time Solar Schools

Total annual school fuel saving (litres)

20,540

Total annual fuel saving 91 teachers' homes getting solar (litres)

4,150

Total annual cartage saving (litres)

3,081

Total annual fuel saving (litres) (4)

27,886

Total fuel saving over 30 years (litres)

836,580

Total annual CO2 saving (kgs)

71,103

Total CO2 saving over 30 years (kgs)

2,133,277

Total annual AUD saving (8)

$ 78,672

Total annual USD saving

$ 53,489

Total annual FJD saving

$ 118,008

Total 30 yrs AUD saving

$ 2,360,160

Total 30 yrs USD saving

$ 1,578,540

Total 30 yrs FJD saving

$ 3,482,640

Assumptions

Fuel cost in the islands in AUD/litre (5)

2.00

Fuel cartage consideration % (3)

0.15

Annual fuel consumption per teacher's home wired (litres) (2)

50.00

Annual generator maintenance consideration AUD (6)

1500.00

CO2 produced per litre of fuel burned (kgs) (7)

2.55

AUD to USD conversion rate used

0.68

AUD to FJD conversion rate used

1.50

Notes

(1) This is the annual fuel consumption based on reporting from the school at the time of school survey and affirmed at the time of installation. It refers to direct fuel use by the school, not including teachers' homes.

(2) The fuel consumption of teachers' homes varies considerable between homes and over time. Their sources of energy varies from their own small generators to shared generators, still some use kerosene for lighting and some small solar (often failing) for lights and charging. Recently on Beqa Island two of the 7 households at one school were each using 10 litres of fuel per week and some were using very little. So, we have chosen the conservative underestimate of each household saving of 2 litres per week (approx. 5 kgs of CO2).

(3) Most schools have a cost to get fuel to the school - usually small boats and car/truck on the mainland. The costs vary from small amounts to some schools where the cartage cost is almost the same as the cost of the fuel itself. The cartage consideration (dollar and carbon cost) is a percentage of the total fuel consumption, because it varies widely from school to school we have chosen quite a conservative estimate.

(4) Includes cartage and teachers' home consumption estimate that therefore contribute to the total CO2 saving. But we do not include the teachers home in the financial saving - rather we just refer to the savings from the school generator.

(5) This is the current published diesel price in Fiji presented in AUD. Often the islands pay a higher price, but that is not factored in, so generally the price will be a small under estimation.

(6) Generators often require repairs and eventually replacement. That cost varies significantly from school to school, so a conservative value is applied to represent this component of cost/saving for all schools. It is not possible to calculate that accurately for every school, hence the estimate across all.

(7) Burning diesel produces CO2 at a rate of 2.68 kgs/litre, whereas petrol produces it at a rate of 2.31 kgs/litre. We have chosen 2.55 as the approximate for our calculations because there is more diesel used than petrol in the school generators.

(8) The fuel savings in the teachers' homes are not included in the calculation of financial savings for the school. Although teachers are asked to make a small contribution each term (FJD70) for their now 24-hour power and this goes to the school to buy more education resources.

Specifications
Document
20 June 2022

DC Coupled

Inverters

Inverter type

Outback FlexPowerTwo

Charge controller

2 x Outback Flexmax 80

Panels

Panel type

Canadian Solar CS3U-380MS

Number of panels

16

Array (watts)

6080

Mountings

Mountings

Ground mounted

Brand

Clenergy Solar Terrace II

Batteries

Battery type

Simpliphi PHI 3.8 Lithium Ferro Phosphate

Number of batteries

6

Kilowatt hours

21.5

Batteries mounted

ICS Industries (Enersys) Cabinet


General electrical works

The school's wiring was very old and dangerous, so the school was rewired including the one teacher's home in the school precinct.


Partners

Solar contractor

CBS Power Solutions

General electric works constractor

CBS Power Solutions


Contacts
Document

Enter all contacts e.g School Manager, Head Teacher, Principal. The more the better.
If a contact changes, for example the principal, edit the old record to show the new person’s details.

New First Name Last Name Position Phone Email FB Note Edited
Charge data
Don't have login?
Document

This data is currently only available to the school and admin.